Our client, a Global Retail & Entertainment Conglomerate (G-REC), is a multinational pioneer and market leader across the retail, leisure and property development sectors in the Middle East, Africa and Asia, operating extensive portfolios of shopping malls, hypermarkets and entertainment venues
G-REC, a leading force in the MENA’s retail and leisure sector, was undertaking a significant digital transformation. This programme involved migrating core business functionality—including supply chain logistics, high-volume retail transactions and financial reporting – onto a consolidated SAP S/4HANA platform. This modern core was closely integrated with its public-facing e-commerce and omnichannel systems (e.g., SAP Commerce Cloud).
The key risk was the system’s ability to cope with massive, unpredictable load spikes during major regional sales and holiday periods (such as Ramadan and the annual “White Friday” events), where transaction volumes were projected to surge by up to 350% above normal traffic. A single performance failure could lead to substantial revenue loss and reputational damage.
The testing initiative required a robust, high-scale solution to:
Testhouse implemented a targeted, “shift-left” performance engineering programme utilising the capabilities of Tricentis NeoLoad to proactively guarantee the stability and scalability of the new SAP landscape.
The programme successfully identified and eliminated critical performance risks, securing G-REC’s system stability and ensuring a smooth transition to the new S/4HANA environment.
| Metric | Outcome | Detail |
|---|---|---|
| Peak Load Validation | 40,000+ Concurrent VUs | Successfully validated the end-to-end platform at 200% of the client’s historical peak load, validating system capacity for future growth.t |
| Response Time Improvement | 55% Reduction | Identified and tuned slow-running transactions, dropping average business process response times for key SAP transactions from over 4.5 seconds to under 2.0 seconds |
| Defect Prevention | 100% Stability Achieved | 19 critical performance bottlenecks (including database deadlocks and slow APIs) were identified and resolved pre-go-live, resulting in zero performance-related issues during the first major holiday trading period. |
| Test Maintenance Effort | 65% Savings | NeoLoad’s low-code design and automatic script maintenance significantly reduced the recurring effort required to update tests after system changes. |
| Test Automation Time | 45% Faster Execution | Test execution cycles were accelerated, enabling the team to run 3x more load tests per sprint than was previously possible. |